cOMPANY:
An Chúirt Hotel
LOCATION:
Gwedore
DATE:
February 23 – March 23
description of works:
We were appointed by the Gallen Hotel Group to upgrade the existing Air Handling Units (AHU’s) that service the leisure facilities at An Chúirt Hotel, Gweedore, Co. Donegal. Works included dismantling and removal of the existing AHU’s and associated ductwork. Our team assembled the new AHU’s in-situ, erected new perforated ‘air sock’ ducting above the swimming pool and reconfigured the existing ductwork within the locker rooms/ health suites. Our Commissioning engineers also undertook witnessed balanced and commissioned of the Air Handling Units on completion. Project Duration 2.5 weeks.